Tracking equipment cost by job: a guide for heavy civil contractors

How to set an internal hourly rate, capture machine hours on site and track equipment cost by task and by job, for heavy civil contractors.

7 min
On this page
  • Why track equipment cost by job
  • Step 1: set an internal hourly rate
  • Step 2: capture hours on site
  • Step 3: allocate cost by task and compare to budget
  • Pitfalls to avoid
  • Frequently asked questions
  • In heavy civil, machines often weigh as much as labor in a job's cost. Yet many contractors don't know what the excavator cost on a given job until the project is over. Here is how to set an internal hourly rate, capture hours on site and track equipment cost by task.

    Key takeaways
    • Equipment cost by job comes from two things: an internal hourly rate per machine and actual hours, captured on site on the right task.
    • The hourly rate combines ownership costs (depreciation, financing, insurance, storage) and operating costs (fuel, maintenance, repairs, wear).
    • Hours should be captured the same day with the operator's, then compared to each task's budget. That's what Civalgo does.
    Contents
  • Why track equipment cost by job
  • Step 1: set an internal hourly rate
  • Step 2: capture hours on site
  • Step 3: allocate cost by task and compare to budget
  • Pitfalls to avoid
  • Frequently asked questions
  • Why track equipment cost by job

    If machine hours aren't tied to the right job and task, three problems show up:

    • each job's real profitability stays unknown until the end;
    • the next bids rely on estimated rates and productivity, not measured ones;
    • you rent machines while your own sit underused on another job.

    For the most common sources of loss, see also our article on equipment management and where the money goes.

    Step 1: set an internal hourly rate

    The internal hourly rate is what one machine hour really costs the company. It's calculated for each machine or machine category and combines two families of costs.

    Ownership costs

    • depreciation (purchase price minus resale value, spread over the useful life);
    • financing;
    • insurance, registration and permits;
    • storage.

    Operating costs

    • fuel;
    • preventive maintenance;
    • repairs;
    • wear on tires, tracks and attachments.

    Divide the annual total by the hours of use expected in the year. The operator's wage stays in labor. Review these rates at least once a year with your accountant, based on actual costs.

    Step 2: capture hours on site

    A good rate is useless without the right hours. There are three sources:

    • the machine's hour meter, read by the operator: reliable for the total, but it doesn't say which task the machine worked on;
    • manufacturer telematics: precise on location and engine time, but it doesn't know your tasks or cost codes either;
    • the operator clocking in with the machine, in the daily report: this is what ties hours to the right task and cost code.

    The most reliable approach is to capture equipment hours the same day, along with the operator's, on the planned task. With Civalgo, the operator clocks in with their machine and the hours go into the signed daily report, even offline.

    Step 3: allocate cost by task and compare to budget

    Actual hours times the internal rate gives equipment cost by task. It adds to labor in the job's actual cost, then is compared:

    • to the task budget, taken from the bid;
    • to actual progress, measured by quantities installed.

    A task that has used a large share of its equipment budget for a small share of its quantities points to a productivity problem, the wrong machine or waiting time. See our page on job profitability tracking.

    Pitfalls to avoid

    • One rate for the whole fleet: a mini excavator and a 30-tonne excavator don't cost the same.
    • Forgetting standby time: a machine parked on a job still costs ownership.
    • Entering hours at the end of the week: task allocations become guesses.
    • Not comparing renting and owning: the internal rate lets you decide, machine by machine, whether to rent or buy.

    Frequently asked questions

    How do you calculate a construction machine's hourly rate?

    Add up its annual ownership costs (depreciation, financing, insurance, storage) and operating costs (fuel, maintenance, repairs, wear), then divide by the expected hours of use. The operator's wage stays in labor.

    How do you track equipment hours by job?

    Have the operator clock in with the machine, on the planned task, in the daily report. The hour meter and telematics give the total, but not the split by task.

    Should the operator be included in the machine's rate?

    Usually not: keeping labor and equipment separate lets you compare each to its budget and reuse the rates in bids.

    What software tracks equipment cost by job?

    Job site software that captures equipment hours along with the operator's and builds them into cost by cost code. For heavy civil in Quebec, Civalgo is built for this. See our construction equipment tracking page.

    Civalgo team
    Written with project managers and controllers from our customers.